PMP Practice Test | Exam 2

Instructions

  • These 25 PMP practice questions are based on PMBOK Guide, 5th Edition and are prepared by the PMP® certified project managers at MyPM.
  • There may be more than one right answer; however, select only one best answer for every question.
  • Want a visual reminder to come back to a question? Place a check mark in the box labelled “Mark for Review.” It’s located at the top right of every question.
  • When you are done, select the button at the bottom of the page. Your exam will be graded and your score will be displayed.
  • Incorrect answers will have a red X next to them while correct answers will have a green check mark.
  • If you are timing yourself, allow thirty minutes.
PMP Practice Test Exam 2

Exam Topics

This exam tests your knowledge of project scope management and project time management. For PMP practice questions that test additional topics, see our other PMP practice exams.

Begin Exam 2

Mark for Review

1. Which technique can be used to determine the cause and degree of the difference between the baseline and actual performance?

 
 
 
 

Question 1 of 25

Mark for Review

2. Change requests can include

 
 
 
 

Question 2 of 25

Mark for Review

3. If a change request is approved and the project scope is revised, what must be revised and reissued to reflect the approved changes?

 
 
 
 

Question 3 of 25

Mark for Review

4. Which of the following is a scheduling method?

 
 
 
 

Question 4 of 25

Mark for Review

5. Without notice, the previous project manager is fired and Tim is the new project manager. Where should Tim look to find which scheduling method and scheduling tool is being used?

 
 
 
 

Question 5 of 25

Mark for Review

6. Which of the following is not a tool or technique for estimating activity duration?

 
 
 
 

Question 6 of 25

Mark for Review

7. The critical chain method is

 
 
 
 

Question 7 of 25

Mark for Review

8. A network diagram is one way to present the

 
 
 
 

Question 8 of 25

Mark for Review

9. A decision to fast track a project schedule could affect

 
 
 
 

Question 9 of 25

Mark for Review

10. The schedule management plan might establish the

 
 
 
 

Question 10 of 25

Mark for Review

11. With Earned Value Management (EVM),

 
 
 
 

Question 11 of 25

Mark for Review

12. Earned Value (EV) is also referred to as

 
 
 
 

Question 12 of 25

Mark for Review

13. The Schedule Performance Index (SPI) is a measure of schedule efficiency on a project. Which of following formulas calculate the SPI?

 
 
 
 

Question 13 of 25

Mark for Review

14. With respect to creating a WBS, the term “decomposition” refers to

 
 
 
 

Question 14 of 25


Mark for Review

15. Sarah is preparing the project activity list which will include the attributes of each activity. Which of the following answers best describe activity attributes?

 
 
 
 

Question 15 of 25


Mark for Review

16. The Shiny New project concerns the custom development of a complex business application. The primary purpose of the new software is to forecast the amount of steel a manufacturing plant must purchase, 90 days before they need it. Today, the in-progress application was presented to the client and a major function was presented. This function presented the ability of the application to make the required forecast. As to the Shiny New project, it reached a major

 
 
 
 

Question 16 of 25


Mark for Review

17. Every activity and milestone except the first and last should be connected to at least one _________ with a finish-to-start or start-to-start logical relationship and at least one ________ with a finish-to-start or finish-to-finish logical relationship.

 
 
 
 

Question 17 of 25


Mark for Review

18. Precedence diagramming method (PDM)

 
 
 
 

Question 18 of 25


Mark for Review

19. The precedence diagramming method (PDM) includes four types of dependencies or logical relationships. Which answer below is not one of them?

 
 
 
 

Question 19 of 25


Mark for Review

20. Which of the following is an example of a finish-to-start logical relationship?

 
 
 
 

Question 20 of 25


Mark for Review

21. Start-to-finish (SF) is a logical relationship in which a successor activity cannot

 
 
 
 

Question 21 of 25


Mark for Review

22. In PDM, _____________ is the most commonly used type of precedence relationship.

 
 
 
 

Question 22 of 25


Mark for Review

23. Bethany is scheduling a project for the construction of a new bike trail. She scheduled the landscaping to start two weeks prior to the scheduled project completion date. This would be shown as a

 
 
 
 

Question 23 of 25

Mark for Review

24. This fishbone diagram illustrates cause and effect. Another name for this diagram is the

 
 
 
 

Question 24 of 25


Mark for Review

25. Jett Kayaks is adding a new manufacturing line and Brandon is the project manager. He estimated the cost of implementing the new manufacturing line at $47,300. He arrived at this amount by reviewing the WBS and adding together all estimates of the lower-level components. This method of estimating cost is called

 
 
 
 

Question 25 of 25


 